Dean’s is close to completing water main installation on Packer Woods Drive, this should be finished up Monday or Tuesday of this week.Next, Dean’s will start water main installation on Rogue Hill Court, and this will take approximately two days. At this same time, the newly installed water main on Packer Woods Drive will be pressure tested and disinfected. Once water main installation is complete on Rogue Hill Court, Dean’s will complete the water main installation on Rogue Hollow Court which will take one to two days.Please contact any project representative to the left if you have questions or concerns.