Progress Report:

Ron Meyer & Associates has started stripping topsoil, filling sand, and adding gravel to multiple sections of the pathway on Perry Street and sections of both 74th and 76th Avenues.

Riverworks has resumed work on the boardwalks, finishing headwalls and constructing wingwalls.

Upcoming Work:

In the coming weeks, Ron Meyer & Associates will continue south on 74th Avenue stripping the topsoil and adding sand. They will also look to begin construction on the concrete block retaining walls and start construction on some portions of storm sewer on 76th Avenue.

Riverworks will continue work on the headwalls and wingwalls for all four of the boardwalk locations.