Underground pipe work is officially underway with the installation of sanitary sewer and water main on Hart Street.  Water main installation on Hart will continue next week.  Also next week, sanitary sewer on Jefferson and storm sewer on Hart will begin.

Work Completed This Week

  • Installation of sanitary sewer on Hart street stopping at Wood.
  • Installation of water main began on Hart.

Anticipated Work Next Week

  • Installation of water main will continue on Hart.
  • Installation of sanitary sewer on Jefferson.
  • Installation of storm sewer on Hart.