The watermain installation project is still slated to begin in September. However, the tree removals are expected to begin next Monday (August 1st) and the crews anticipate they will complete all the tree removals planned for Phase I. Trees currently scheduled for removal are flagged with a pink or yellow ribbon.

The City of Grand Rapids has approved two plumbing companies to complete the installation of water services between the watermain by the road and your basement. The contact information is listed below, as is a process of how the work is expected to be completed.

 

Pre-approved Plumbing Companies:

McDonald Plumbing
Attn: Grace Thumser
(616) 698-6771
gthumser@mcdonaldplumbing.com

BRIK Plumbing
Attn: Kraig Keegstra
(616) 277-1561
kraig@brikplumbing.com

 

Process for Plumbing Selection: