Work this week focused on road building from Southern to Strong and utility replacements from Laketon to Southern. Road building is in full swing with the targeted road opening date fast approaching.

 

Work Completed This Week

  • Public and private side water services on phase III.
  • Installation of sanitary sewer on phase III started.
  • Placement of curb & gutter and sidewalk on phase II began.  All straight mainline curb has been completed.
  • Various water system improvements were completed on phase III.

 

Anticipated Work Next Week

  • Continue placing curb & gutter and sidewalk on phase II.
  • Continue building road on phase II, paving of the first course is schedule for Wednesday, depending on weather.
  • Complete placing public and private side water services on phase III.
  • Continue placing sanitary mainline on phase III.
  • Perform watermain tie-in on phase III on Tuesday.