Progress Update
Sanitary sewer installation on Crystal Ave, Highland Ave, Vashti St has been completed, with the exception of one lateral to complete.
Up Next
Construction of the road gravel base on Highland and Vashti St will begin next week and continue over the next couple of weeks, before paving on all 3 streets will occur.