Progress Report:

This week Miller Bridge was focused on preparing the concrete forms for the pile columns. They installed several forms and prepared the columns for concrete.

Upcoming Work:

Next week the contractor will continue the preparation work on the remaining concrete forms and plan to begin pouring the concrete for the pile columns. The pathway work is planned to continue with removals and pathway grading near the intersection at 144th Street and Green Street as they prepare to pour the sidewalk ramps.