The focus this week was on placing sanitary sewer main for Phase I on Griswold Street. The focus next week will be on continuing to place sanitary sewer main line. 

 

Work Completed Last Week

  • The Contractor continued placing sanitary sewer main on Griswold Street for Phase 1.

 

Anticipated Work This Week

  • The Contractor will continue placing sanitary sewer mainline and sanitary sewer manholes for Phase I.