Work Completed this Past Week:
- Completion of removals of driveway approaches and concrete curb and gutter on 7th Street, between Oakwood and Summit and on Amsterdam between Highland and 6th
- More materials and equipment were delivered to the site
- Water main pipe was installed between Oakwood and Amsterdam
Work Anticipated Week of August 28, 2023
- Continued water main installation between Amsterdam and Summit
- Begin scheduling for water service replacements in middle of September 2023
Work Anticipated Week of September 4, 2023 (Labor Day)
- No work on Labor Day
- Continued water main installation and potentially tie-in one segment
- Possibly begin preparing for water service installations