Progress Report:
Drilling for the horizontal directional drill (HDD) under Macatawa River began this week. Gabe’s ran into some technical issues early in the week which have been resolved. As of Friday (23rd), approximately 600 linear feet of the pilot drill has been compete. The total length of bore is about 2,000 linear feet.Additional traffic control measures were implemented to make the traffic shift along River Avenue clearer, and additional signage for the pedestrian detour was also implemented.© 2024 Prein&Newhof, All Rights Reserved