Work Completed this Past Week:

  • Staking was done for the future island that will be where the path will cross the Glenside south of the Railroad
  • Material was removed to make room for road base gravel north of the railroad tracks

 

Work Anticipated Week of August 28, 2023

  • Grading south of the railroad tracks will take place
  • Road base gravel will be delivered beginning Tuesday and begin to be spread, compacted and shaped

 

Work Anticipated Week of September 4, 2023 (Labor Day)

  • No work will take place on Labor Day
  • Continued delivery and placement of road base gravel and preparations for concrete curb and gutter installation

 

Construction will still remain on schedule for being completed in September 2023.