Work Completed this Past Week:

  • Staking was done to mark out removal limits on Seng, Kunz and Aue
  • Sawcutting of Pavement on Seng, Kunz and Aue
  • Pavement removal, including driveway approaches on the west side of Seng between Eugene and Hile
  • Water main pipe was installed on Seng between Eugene and Hile
  • Residents on Seng – Temporary mailboxes were moved to Hile and will be moved to Eugene at the request of USPS on Monday, August 28, 2023.

 

Work Anticipated Week of August 28, 2023

  • New water main on Seng Road will be tested and if passed, will be tied to the existing water distribution system
  • Pavement removals and driveways on the west side of Kunze between Eugene and Hile
  • New water main pipe will be installed on Kunz Street between Eugene and Hile
  • Residents on Kunz – Mailboxes are not planned to be relocated since work will not be done on the side of the road that the mailboxes are on.

 

Work Anticipated Week of September 4, 2023 (Labor Day)

  • No work will take place on Labor Day
  • New water main pipe on Kunz will be tested and if passed, will be tied to the existing water distribution system
  • Pavement removals and driveways on the north side of Aue Road east of Miller
  • New water main pipe will be installed on Aue Road east of Miller

 

Construction is scheduled to be completed in November 2023.  Please watch for more information about connecting to the new water main for those residents connecting to the new water main.