Work Completed This Week
- Jackson-Merkey Contractors, Inc. finished installing sanitary sewer on Jefferson Street and began installing sanitary sewer on Strong Avenue between Jefferson Street and Sanford Street.
- The contractor began installing storm sewer on Jefferson Street at Strong Avenue.
Anticipated Work Next Week
- The remainder of the storm sewer on Jefferson Street will be installed early next week.
- Sanitary sewer installation will continue on Strong Avenue east toward Peck Street.
Current Road Closures
- Mason Avenue from Third Street to Fourth Street.
- Strong Avenue from Fourth Street to Sanford Street.
- Jefferson Street from Campus Street to Monroe Avenue.
- Sanford Street at Strong Avenue.