Hallack Contracting spent this week finishing the install and testing of the water main and began installing storm sewer.
Work Completed This Week (August 24 – 28)
- Hallack Contracting completed the water main main line installation.
- Hallack completed testing of the water main.
- Hallack started storm sewer construction.
Anticipated Work Next Week
- Following the final passing of bacteria testing, the water main will be connected to the existing system.
- Water services will start to be installed towards the end of the week.