Work this week was focused on storm sewer around the Mohawk intersection, which is now nearly complete.

Work completed:

Anticipated work for next week:

 

As concrete is placed there may be times when drives are inaccessible for a few days while the concrete cures. Contractor will work with you to let you know prior to pours so that vehicles do not get trapped in your driveways.