This Week

Construction crews completed testing of the water main along with connection of the new main to Fieldstone and Division Street Main.

Water services are being installed and are about 50% complete with short side services (those properties on the same side of the road as the water main) complete.  Long side services are anticipated to be completed this week.  Connection of the new main at Center Street is anticipated the week of August 15.

The new sanitary sewer has been connected at Center Street and installed to the west past Oriole Street.  Sanitary sewer work will resume once water services are complete.

Crews began removal of pavement on Greenfield in preparation of the long side water services and sanitary sewer.