Progress Update

Approximately 2,150 feet of sanitary sewer and 2,250 feet of watermain have been installed to date, as shown on the map above. Both the sewer and watermain crossing under the recently completed MDOT I-94 Business Loop has now been completed.

Up Next

Watermain installation is planned to continue through the end of the week along Euclid Ave up to Highland Ave.