Search
Close this search box.

Gravity Sewer Construction

Gravity sewer installation between the new lift station site and the Brookfield Car Dealership has continued over the last two weeks. Approximately 350’ of 36” sewer has been installed. 36” sewer installation will continue through the end of the week.

 

Lift Station

The meter chamber and the valve chamber piping at the lift station have been installed.