Last Week

All of the piles in Boardman Lake are now set and proofed! There are three remaining sets of piles to be placed, but they are mostly out of the water and will be placed from the NMC side in the near future. The swamp excavator and barges will now be able to leave the lake. Spence Brothers continued to work on the deck, and also set the footings for the stairs at the City Park property.

 

This Week

Elmer’s intends to focus on placing the sheet piles around the bridge abutments. They will start on the abutment at Logan’s Landing and work east for the three others. They anticipate this will take them about a month. In the meantime, Spence Brothers will continue to work on the boardwalk deck and the stairs.