Progress Report:
Work completed/in progress:
- Construction began at the Wastewater Treatment Plant in November 2024.
- Dean’s Excavating, the contractor, has completed berm repairs for one of the wastewater ponds, installed three new gate valves in one of the transfer structures, and installed two underground pipelines that will provide the ability to isolate and bypass parts of the Wastewater Treatment Plant.
Upcoming Work:
Anticipated work activities for the coming month:
- With the exception of some minor structure repair work at the Wastewater Treatment Plant, Dean’s will likely be off site until the spring.