The focus last week was on Phase II sanitary sewer at Morrall Street, as well as, water main tie-ins. This week, work will continue on Phase II sanitary sewer mainline and laterals.

 

Work Completed Last Week

  • Phase II sanitary sewer at Morrall Street.
  • Phase II water main tie-ins.
  • Phase II hydrant installation.

 

Anticipated Work This Week

  • Phase II sanitary sewer mainline.
  • Phase II sanitary lateral.