Work Completed This Week

  • Performed 9 water service replacements. All water service placements are now complete.
  • Removed road cones, signs & barricades from Phase 1 of project.
  • West Michigan Sprinkling on site to begin repairing damaged sprinklers on Phase 1.
  • Water main tie-ins at intersections began on Saturday.

 

Anticipated Work Next Week

  • Contractor will be performing water main tie-ins on Tuesday.
  • The sanitary lateral crossing Laketon Ave. to Marsh Field is scheduled to be replaced by pipe bursting and the remaining sanitary manholes will be installed.
  • Kamminga & Roodvoets will begin placing storm sewer on Phase 2.
  • Road striping on Phase 1 of Peck Street will be installed.