Work completed to date:

  • Excavation of site, preparation of construction area for new Local Pump Station and Headworks Building (April – May 2019)
  • The location of the new Local Pump Station and Headworks Building, prepped for excavation
    • Slabs, walls, and decks for the Local Pump Station wet well and valve chamber, and meter chamber for the Headworks were formed and poured (May – June 2019)
  • Remainder of 16” Spring Lake force main was installed—connecting to the new meter chamber (July 2nd)
  • Rise well, grit chamber, and grit outlet channel base slabs were formed and poured (July 11th, 2019)

 

Anticipated work this month:

  • Start process piping and valves in wet well, valve chamber, and meter chamber
  • Install electrical duct banks in yard
  • Form and pour grit chamber, rise well, and grit outlet channel walls
  • Pour fillets in the Local Pump Station wet well