Work completed:

  • Completed construction of the retaining wall for the new path.
  • Removed curb at intersection of Dogwood Drive and Mohawk Drive.
  • Removed sidewalk section southeast of Dogwood Drive and Mohawk Drive near the bike crossing.
  • Started construction of new storm sewer and catch basins.

 

Anticipated work for next week:

  • Work on the new storm sewer will continue.
  • If storm sewer is complete, the Contractor intends to relocate existing fire hydrants.

 

As storm sewer work continues this will require momentary full road blockages.  These blockages will be removed by evening.