Progress Report
On Friday, July 17 the crew was back on site preparing the area along Leonard for a new retaining wall.
What to Expect This Week
- You will notice more equipment moving around on site. The crews are preparing and bringing in equipment for the boardwalks and retaining walls. They will also begin grading the path along Leonard this week.
- Shoulder closures on Leonard will continue this week as the retaining wall crew works along the shoulder. Please be mindful of our safety and your speed where workers are present.