Progress Report:

This week Milbocker installed all new water services in the public road right-of-way along Eldon Street. The two water main tie-ins (connection of new water main to existing water main) were completed at the intersection of Eldon Street and Northgate Street. Milbocker also completed some storm sewer work at the intersection of Eldon Street and Northgate Street. Milbocker is going to start working Saturdays this week and plans to continue this throughout the rest of the project. Now that the water main construction along Eldon Street is complete Milbocker is going to start installing new water main along Miramar Avenue, working from Eldon Street north to Airway Street.

Upcoming Work:

Milbocker will have a second crew on site next week to begin sidewalk and driveway restoration along Eldon Street. Milbocker will continue installing new water main north along Miramar Avenue.