Much has happened over the last two weeks. The beginning of the project focused on Water Street, and the focus now is on Washington Avenue.

 

Work completed:

  • Sanitary sewer is 95% complete and only requires one final short run to be completed on Washington Avenue.
  • Subgrade under cutting and grading is complete on Water Street with some of the final gravel being placed.
  • Water main on Washington Avenue has been installed from Water Street up to mid-block between 1st Street and 2nd Street.

 

Anticipated work for next week:

  • Complete the sanitary sewer.
  • Finish installation of the mainline water main up to 2nd Street and begin testing and the disinfection process of the main.
  • Begin constructing the storm sewer on Washington Avenue between Water Street and 2nd Street.