Underground utility work continued this week on Dryden Street with sanitary sewer installations from Wood to Wigton Street. Sanitary sewer installation will continue, while storm sewer begins on Wood Street next week.
Work Completed this Week
- Sanitary sewer main installation on Dryden from Wood Street to Wigton Street.
- Sanitary lateral installation on Dryden from Wood to Wigton.
Anticipated Work Next Week
- Sanitary sewer main installation will continue on Dryden Street.
- Sanitary sewer lateral installations will continue on Dryden.
- Storm sewer installation will begin on Wood
Please Note: Underground utility work continues on Wood street. Dave’s party store is accessible on Hart Street from the north.