Underground utility work continued last week on Wood Street, connecting the new water main into the existing system at Union, Hart and Dryden.  Underground utility work will continue on Wood Street this week beginning sanitary sewer at Union working west.

 

Work Completed last Week

Anticipated Work Next Week

Please Note: Underground utility work has begun on Wood street. Dave’s Party Store is accessible on Hart Street from the north.