To all residents on Crowley Street:

The contractor will be installing concrete curb and gutter on Crowley Street this week.  The concrete will take up to a week to cure before vehicles will be permitted to drive over it.  Curb and gutter will be installed on Crowley St. according to the following schedule:

Tuesday, June 2: Windsor Ave. to Laketon Ave.

Friday, June 5: Young Ave. to Windsor Ave.

At those times, the road will be closed to ALL traffic and residents will not have driveway access for up to a week after installation.  If you live on Crowley Street, please remove any vehicles you may need from your driveway prior to curb and gutter installation. Parking access in front of residences will be maintained after construction hours and overnight. Thank you in advance for your flexibility, new asphalt is in sight!