The focus this past week was on placing driveway approaches and sidewalk, as well as, the base course of asphalt. The focus this week will continue to be on installing sidewalks and driveway approaches, as well as the top course of asphalt.

 

Work Completed Last Week

  • Contractor placed sidewalk and drive approaches.
  • Contractor completed fine grading of aggregate.
  • Contractor placed base course of asphalt road.
  • Contractor began restoring turf.
  • Contractor milled asphalt on phase 2 of Sanford St. from Morrall to Southern.

 

Anticipated Work This Week

  • Continue placing sidewalk and drive approaches.
  • Placing top course of asphalt pavement on Tuesday, June 13th.
  • Continue restoring turf.
  • Begin irrigation repairs.