Significant progress was made this week on rebuilding the roadway east of Gaylord with concrete work being completed. The end is in sight!
Work Completed This Week
- Concrete Curb and Gutter, sidewalk, and drive approaches were installed east of Gaylord.
- Aggregate was placed east of Gaylord.
Anticipated Work Next Week
- Final grading of the gravel.
- Paving of the first course of asphalt east of Gaylord is scheduled for the end of the week.
- Street sign installation.