Road rebuilding is the main focus right now with paving on Center and spreading aggregate on West.
Work Completed This Week on West
- Sand grad was cut and aggregate is begin placed working south from Apple Avenue.
Work Completed This Week on Center
- Final paving was completed.
- Gravel shoulder installation was started.
Anticipated Work on Center
- Final restoration work.
Anticipated Work on West
- Grading and compaction of sand in preparation of gravel installation.
- Gravel installation for the east lane.
- Crushing the west lane and grading both lanes for the new roadway