Last Week:
- Northville Drive was milled on Tuesday and Wednesday.
- Concrete driveway work took place on Wednesday.
- Paving of Northville Drive was completed on Thursday.
- Paving of intersections was completed on Friday and select asphalt driveways were milled due to grade issues with the new road.
This Week:
- Black Gold and K&R are not anticipated to be on site this week to allow the new asphalt adequate time to cool down.
Remaining Work:
- Black Gold will be back on site to pave the asphalt driveways which have been milled down. The exact date of this work is TBD.
- K&R will be on site after the driveway work is completed and will touch up lawn restoration along the road and driveway edges.
Please contact any project representative if you have questions or concerns.