Progress Update

Sanitary sewer installation on Francis Ave and Eastman Ave has been completed. Approximately 1,600 feet of sanitary sewer installation on Britain Ave has been completed. The progression of sewer installation is moving more quickly now because of shallower excavation in this section of the project.

 

Up Next

Sanitary sewer installation on Britain Ave will continue over the next couple of weeks. Paving on Britain Ave and Eastman Ave is anticipated to occur the week of June 27.