Progress Update: Sanitary sewer installation on Crystal Ave north of the I-94 Business Loop roundabout has been completed. Approximately 400 feet of sanitary sewer installation on Crystal Ave south of the I-94 Business Loop roundabout has been completed. Progress is moving relatively slowly because of deep excavation in this section of the project.

Up Next: Sanitary sewer installation on Crystal Ave south of the I-94 Business Loop roundabout will continue over the next few weeks before starting on Highland Ave. The Highland Ave/Crystal Ave intersection will remain closed until sanitary sewer installation on Crystal Ave is complete.