Progress Update

Sanitary sewer installation on Crystal Ave north of the I-94 Business Loop roundabout has been completed. Approximately 400 feet of sanitary sewer installation on Crystal Ave south of the I-94 Business Loop roundabout has been completed. Progress is moving relatively slowly because of deep excavation in this section of the project.

 

Up Next

Sanitary sewer installation on Crystal Ave south of the I-94 Business Loop roundabout will continue over the next few weeks before starting on Highland Ave. The Highland Ave/Crystal Ave intersection will remain closed until sanitary sewer installation on Crystal Ave is complete.