This Week

Paving has been completed for the trail and parking lot! All pavement markings, including parking striping at Medalie Park, is complete! In addition, all concrete work and paver bricks are installed and complete. Grass seeding and final restoration began this week.

 

Next Week

Grass seeding and restoration should be completed next week, as well as much of the plantings and special shoreline restoration.

After that, some plantings, cleanup, and punch list reviews will be completed and the project should be open very soon.