Progress Report:
New Pump Station site work continues as K&R finalizes the trench box rail system installation in preparation for concrete work in the coming weeks. These rail systems are used to minimize site impact due to trench excavation and ensure safe work conditions.
Upcoming Work:
Next Steps: Pump Station No. 31 concrete work for the wet well and the CSX/Lakewood Blvd bore & jack operations to begin later March and extend into May.