The exterior metal work on the Crooked Lake filter building has been completed. As well as both in interior and exterior concrete work.

Upcoming Schedule:

  • Construction of Crooked Lake Pump Station filter building & wet well will continue.
  • Balkema will begin construction of the access drives to Crooked Lake filter building and wet well.
  • Underground piping at Eagle Lake has begun to be fused and installation will begin soon.
  • Underground structures have been delivered to the Eagle Lake site and installation will begin soon.