Last Week:
- Gas main work continued around Herrington Avenue in preparation for the road to be lowered at this intersection.
- The existing asphalt was milled off the north portion of 10 Mile Road in preparation for road work to begin soon.
- Brenner Excavating continued to install 16-inch water main along 10 Mile Road near Pine Island Drive.
- Brenner Excavating connected the new water main to the existing water main at Jewell Avenue.
This Week:
- Brenner Excavating will start installing water service stubs for each house at Jewell Avenue.
- Dewatering equipment and pumps will be set up so that the 16-inch water main installation can continue.
- It is anticipated that water main construction will continue later this week.
Please contact any project representative below if you have questions or concerns.