Last Week:
- Lab test results have proven the treatment system is removing the PFAS from the groundwater and can now be discharged to the sanitary sewer system.
- DeSal Excavating began to move equipment to the site.
This Week:
- DeSal will continue moving equipment and material on site and intends to start water main construction early in the week.
Please contact any project representative below if you have questions or concerns.