This week was a very productive week despite the weather delays. Work was completed on water main, sanitary sewer, road grading, sidewalks, and curb. Rebuilding of Edgewater is in full swing with completion around the corner.
Work Completed This Week
- Concrete sidewalk replacement was completed on Edgewater between Thompson and Wilcox.
- Curb and Gutter was placed on Edgewater between Thompson and Wilcox.
- Sanitary sewer was installed on Walnut, about 100 ft of progress was made on the sewer.
- Water main installation was completed on Walnut to approximately 2/3 of the way to Wilcox.
Anticipated Work
- Water main installation will continue on Walnut and Thompson towards Plum. Testing for this main may begin near the end of the week.
- Work on sanitary sewer will continue with services on Thompson.
- Concrete drive approaches will be placed on Edgewater.
- Final grading of aggregate will be completed on Edgewater.
- The first course of asphalt will be placed on Edgewater between Thompson and Wilcox. If time allows the top course will be placed too. Note this pavement will be placed to include the east half of the Edgewater and Wilcox intersection, the west half will remain gravel until Wilcox is completed. Pavement will extend up through the Thompson and Edgewater(south) intersection.
Please do not write in the concrete or drive across it until the contractor indicates that you may.