This week the focus was on water service installations and restoration. Densmore and East Street restoration is now complete less minor clean up items. No work was completed on Center Street but work will be starting there again this coming week.
Work Completed This Week on West
- Water testing was begun on the water main south of Vine and will continue into the next week.
- Water service installation north Vine started and good progress was made.
Work Completed This Week on East and Densmore
- Final topsoil spreading, raking and seeding was completed.
- Water meter pit installation was completed on East Street.
Anticipated Work on Center
- Reconstruction of the roadway will begin on Monday. This will take approximately 2 weeks to complete.
Anticipated Work on West
- Water service replacements will be the primary focus this week.
- Testing of the water main south of Vine will be completed.