Progress Report: K&R made approximately of progress with sanitary sewer construction to the north. Pipe Installation is approximately to 350 feet south of Randall Street. Also, K&R started storm sewer construction behind sanitary sewer installation.
Upcoming Work: K&R will continue sanitary sewer construction progressing to the north. K&R will also start sanitary lateral connections and continue storm sewer construction on River Street in the area where sanitary sewer construction has been completed.
Extra Notes: During sanitary sewer construction, River Street will be blocked off for through access at the location of the sanitary sewer excavation. As sewer construction continues north, the direction of access to each property will be affected and will change with the progress of construction. Vehicles will have to access their property from either O’Malley or Randall Ave.
Driveway access to River Village and The Meadows is expected to be impacted next week. K&R has constructed a temporary gravel driveway between the parking lots of the two communities. Access to the complexes will be maintained utilizing either entrance, depending on which one is affected by sanitary sewer installation.