Progress Report: The Contractor mobilized a groundwater treatment unit situated on the intersection of Ferry St and Park Ave to treat contaminated groundwater encountered during water main construction. Storm sewer replacements were completed at the Colfax and Waverly intersections. McCormick Sand also installed water main on Ferry Street to the south, making progress to north of Park Avenue.

Upcoming Work: The Contractor will continue water main installation on Ferry Street to the south. Storm sewer replacement and road restoration efforts will start to follow behind the water main construction.

Extra Notes: Residents and motorists are reminded to stay clear of construction equipment and excavations on the project site. As water main construction continues south, access to each property will be affected and will change with the progress of construction.