Progress Report:
Montgomery Excavating completed the installation of water main on Vida Circle this week, and started the installation of water main on Venna Place starting on the cul de sac. Water main progress on Venna Place was made to approximately 200′ south of Ann Street.
Upcoming Work:
Montgomery Excavating will continue water main installation on Venna Place towards the north. The newly installed water main on Vida Circle will be connected to the existing water main on Ann Street this week. Montgomery Excavating will continue pavement removals on both streets this week.
Extra Notes:
Residents and motorists are reminded to stay clear of construction equipment and excavations on the project site.
A water main shut down will occur this week Thursday, May 23rd from approximately 9:00 am to 4:00 pm to accommodate the new water main on Vida Circle being connected to the water main on Ann Street. The City will notify which residents in the project area will be affected by this shut down.