Progress Update

The easement between Bridgman Ave and Crystal Ave has been obtained and the tree removal work in the easement has been completed.

 

Up Next

Sanitary sewer installation is scheduled to occur this week between Bridgman Ave and Crystal Ave. This is the last run of sewer to be installed on the project.