Work Completed This Week

  • Placed 1 sanitary sewer lateral and 220 feet of sanitary sewer main to the south limits of Phase 1 at Southern Avenue.
  • Placed 900 feet of 8 inch mainline water main and installed water main crossings at various intersections.
  • All water main has now been installed within the Phase 1 project limits and is prepped for pressure testing next week.
  • Passed bacteria testing on the water main from Strong Ave. to north end of project limits.
  • Performed watermain tie-in to existing watermain at North end of project limits.

 

Anticipated Work Next Week

The primary Contractor anticipates:

  • Pressure and bacteria test remainder of water main from Strong Ave. to Southern Ave.
  • Begin placing storm sewer at north end project limits.
  • Begin installing water services between Strong Ave. and North project limits.
  • Continue placing sanitary laterals through phase 1.

 

The Contractor did not work on Saturday, May 1.