Pump Station: Progress continues to be made on the pump station site as the wet well walls as Jelsema plans to pour the second half of the wetwell wall this week.
Force Main: Lowe completed the bore & jack under Lakewood Blvd last week. The 30″ HDPE force main carrier pipe was pushed through the casing and the connection was made on the Macatawa Bank property. K&R is now working to complete the force main installation along River Hills Drive.