This project is now in full swing. Last week focused on roadway removal, concrete removals and water main installation began!

 

Work Completed Last Week

  • The asphalt roadway was removed. Portions of the concrete roadway were removed as well.
  • Curb and gutter, driveways and some sidewalk were removed from Denmark to Leboeuf.
  • Water main installation began starting at Denmark Street.

 

Anticipated Work

  • Roadway and concrete removals will continue.
  • Water main installation will continue moving west to Leon and beyond.